Return of Empty Shipping Containers
What Is Empty Container Return?
Empty container return refers to the process of returning empty containers to the return location designated by the shipping line or NVOCC after the devanning operation is completed in import FCL.
In import FCL, loaded containers are taken out from the CY, cargo is devanned at the delivery destination or warehouse, and then only the empty container is returned.
In practice, this process is referred to as "empty container return," "empty van return," "container return," "Empty Return," or "Empty Container Redelivery," among other terms.
In import FCL, cargo removal does not conclude the operation. The full process includes returning the empty container, within the deadline, to the correct return location and in acceptable condition.
Delays in empty container return may result in additional charges such as Detention fees. Moreover, if container damage is identified upon return, verification of repair, cleaning, and damage costs may be required.
This article focuses on the final stage of import FCL: empty container return. It organizes key points such as return locations, return deadlines, devanning operations, drayage, Detention, Demurrage, Storage, container damage, Equipment Interchange Receipt (EIR), and management methods for multiple-container shipments.
Scope of This Article
| Item | Contents Covered in This Article | Details Covered in Other Articles |
|---|---|---|
| Basics of Empty Container Return | The process of returning empty containers to designated locations after devanning in import FCL | The overall flow of import FCL is organized in detail in the article covering integrated import FCL arrangements. |
| Positioning within Import FCL | Viewing the sequence from CY gate-out, drayage, devanning, through empty container return as a continuous import process | Details on CY gate-out, D/O procedures, and import customs clearance are covered in specialized articles. |
| Confirming the Return Location | Confirming depots, CYs, terminals, and return locations designated by shipping lines and NVOCCs | Details on changing return locations, port congestion, and re-arranging drayage are covered in drayage-related articles. |
| Return Deadline and Free Time | Empty container return deadlines, free time, and the relationship with Detention charges | Calculation methods, billing verification, and cost responsibility for Detention are explained in detail in Detention-related articles. |
| Differences between Detention, Demurrage, and Storage | Distinguishing Detention charges, which often become problematic in empty container returns, from other fees | Individual calculation and billing practices for Demurrage, Storage, and Detention are covered in their respective specialized articles. |
| Relation to Devanning Operations | Process linkage where delays in completing devanning cause delays in empty container return | Seal verification, quantity checks, cargo incidents, and receipt notes during devanning are discussed in detail in "What Is Devanning?" |
| Container Condition and EIR | Checking container condition upon return, EIR, and relation to damage records | Inspection of damages, photo records, repair and cleaning costs, and understanding the EIR are explained in detail in the "Container Damage" article. |
| Multiple Container Shipments | Managing return deadlines, return locations, return status, and damage presence by container number | Overall process management of large import shipments and dispatch management for multiple delivery destinations are detailed in the integrated import FCL arrangement article. |
The Role of Empty Container Return in Import FCL
The process flow for import FCL proceeds as follows: vessel arrival, D/O procedures, import customs clearance, CY gate-out, drayage, devanning, and finally empty container return.
Among these steps, the return of empty containers is the final stage in import FCL logistics.
From the cargo owner’s perspective, the transportation might seem complete once the cargo arrives at the warehouse or delivery destination. However, in freight forwarder operations, the FCL transport is not considered finished until the empty container is returned and checks are made to ensure there are no delays in return, Detention charges, container damage, or issues noted on the Equipment Interchange Receipt (EIR).
In particular, with import FCL, delays in earlier stages often become apparent as delays in empty container return. Reasons such as delays in CY gate-out, congestion at the devanning location, inability to secure drayage vehicles, or missing the return terminal’s acceptance hours can ultimately surface as Detention claims.
Basic Procedure for Import FCL
| Process | Main Content | Relation to Empty Container Return | Practical Notes |
|---|---|---|---|
| Vessel Arrival | The import vessel arrives and the containers are discharged at the port. | This may affect the calculation of free time and various charges. | Confirm not only the arrival date but also the earliest pickup date. |
| D/O Procedures | Complete the Delivery Order related procedures necessary for cargo release. | Delays in D/O procedures delay CY gate-out, impacting the return deadline. | Document deficiencies may pressure the entire subsequent process. |
| Import Customs Clearance | Submit import declaration, obtain Import Permit, and respond to inspections. | Customs clearance delays push back devanning and container return schedules. | Allow extra time for customs inspections or checks under other regulations. |
| CY Gate-Out | Move the loaded container out from the CY. | Post gate-out, managing the return deadline becomes practically important. | Coordinate gate-out date, drayage arrangement, and consignee's receiving conditions. |
| Devanning | Remove cargo from the container at the consignee or warehouse. | Empty containers cannot be returned until devanning is complete. | Check availability of workers, forklifts, and devanning space. |
| Empty Container Return | Return the emptied container to the designated location. | Charges such as detention may occur if the deadline is missed. | Confirm the return location, reception hours, EIR, and container condition. |
Confirming the Return Location
Empty containers should not be returned just anywhere.
They must be returned to the depot, container yard, terminal, or designated return location specified by the shipping line or NVOCC.
Even within the same port area, the return location may vary depending on the shipping line, container type, return date, depot congestion, and empty container repositioning plan.
Incorrectly returning containers may result in re-handling, additional drayage charges, delayed returns, or refusal of acceptance. Therefore, the return location should always be confirmed with the latest information rather than relying on old instructions or past experience.
Background on Specifying the Return Destination
The reason for specifying the empty container return destination lies in container equipment management by shipping lines and NVOCCs.
Containers are not disposable per cargo shipment; after import, the empty containers must be returned for the next export, relocated to another port, repaired, cleaned, or stored.
In regions with high import volumes, empty containers tend to accumulate, while in regions with high export volumes, empty containers are often in short supply. To balance this regional imbalance of empty containers, shipping lines designate specific depot or terminal return points to maintain the next transportation cycle.
Depots themselves have limitations in storage capacity, reception hours, gate processing capacity, and repair/cleaning capabilities. If the designated return location is full, the return destination may be changed or reception hours restricted.
Freight forwarders should not treat the return location as mere address information but must verify it as a practical condition affecting container equipment management, depot congestion, drayage arrangement, and return deadlines.
Importance of Return Deadlines
Managing the return deadline is crucial in empty container returns.
In imported FCL shipments, free time may be granted during which no additional charges will apply. Returning the empty container after this period could result in additional fees such as detention charges.
The return deadline should be understood not simply as the day the cargo is devanned, but as the day the empty container is returned to the designated location.
Even if the container has been devanned, returning it after the receiving office’s cutoff time may result in the return being recorded on the next business day. During holidays, weekends, month-end, or port congestion, a one-day delay in processing can lead to extra charges.
Reasons for Differences in Free Time and Detention Terms
Free time and detention terms may vary depending on the shipping line, NVOCC, route, contract, container type, and cargo conditions.
This is not simply because each company has different rate schedules. Operational factors such as container equipment supply and demand, congestion on specific routes, port and inland transportation delays, and the urgency to quickly reuse containers for the next export shipment all have an impact.
For example, on routes or in regions where empty containers are scarce, stricter control over late returns may be imposed. Conversely, in areas where excess empty containers tend to accumulate due to import surpluses, operational practices may differ.
In addition, when the cargo owner contracts directly with the shipping line, when using an NVOCC House B/L, or when a freight forwarder uses a master contract, the applicable free time, invoicing party, point of contact for confirmation, and possibilities for negotiation can vary.
Therefore, when verifying detention charges, it is necessary to confirm not only the cost name but also which contract, which B/L, which container number, and which period the charges apply to.
Relation to Detention
Detention may be categorized as a charge incurred when a container is used beyond a certain period after being gated out from the CY.
In import FCL, container return may be delayed due to reasons such as delayed devanning, the consignee being unable to accept delivery, inability to arrange a return vehicle, or congestion at the return location.
Detention charges are often not visible to the cargo owner. Even if the cargo has already arrived, charges could accrue if the empty container return is delayed.
Therefore, the freight forwarder needs to manage not only the delivery date but also the empty container return date.
Differences Between Demurrage, Detention, and Storage
| Charge Name | Primary Situations Involved | Relation to Empty Container Return | Practical Confirmation Points |
|---|---|---|---|
| Demurrage | When a loaded container remains at the CY or terminal for an extended period | Occurs mainly before the empty container return stage, while the container is still at CY before gate-out. | Check vessel arrival date, earliest gate-out date, free time, and actual CY gate-out date. |
| Detention | When container use extends long after CY gate-out, causing late return | Most directly related to delays in empty container return. | Verify CY gate-out date, devanning date, return date, return deadline, and container number. |
| Storage | When cargo or containers are stored at the terminal, storage yard, or warehouse | May be charged as fees for storage inside the CY or at separate storage locations. | Confirm who is bearing storage costs and whether charges are terminal fees or warehouse fees. |
| Combined / Merged Free Time | When demurrage and detention are managed as a single combined contract | Requires consideration of the entire period before and after gate-out, not just the return deadline. | Check shipping line or NVOCC tariff, contract terms, and application conditions per B/L. |
Possibility of Detention Fee Reduction or Negotiation
Even if detention fees are incurred, it does not always mean that the full amount must be accepted as is.
However, whether there is room for reduction or reconsideration depends on the cause of the delay, contractual terms, the invoicing party, supporting evidence, and the history of business relations.
For example, if there are circumstances that are difficult for the shipper, cargo owner, or freight forwarder to control, such as a sudden change in the return location, depot acceptance restrictions, delayed instructions from the shipping line, customs inspections, public procedures causing delays, adverse weather, or port congestion, there may be room to verify the charges or negotiate a fee reduction.
On the other hand, if the delay is caused by insufficient cargo preparation on the consignee’s side, the consignee’s inability to accept delivery, delays in devanning operations, or poor coordination of yard activities, negotiations for reduction may be difficult.
The important point is not to dispute the detention charge based on intuition when receiving the invoice but to organize information such as container number, gate-out date, return deadline, devanning completion date, actual return date, return location, cause of delay, and communication records with involved parties.
Relation to Devanning Operations
Empty container return is directly linked to devanning operations.
If devanning is not completed as scheduled, returning the empty container is not possible.
Return delays may occur due to congestion at the devanning location, shortage of workers, forklift shortage, cargo damage inspection, or delayed acceptance at the delivery destination.
In particular, if cargo damage or wetting is discovered, work may be halted for photographing, inspection, and contacting the insurance company and related parties. Even in such cases, the deadline for empty container return continues to progress, so it is necessary to keep both incident verification and return deadlines in mind simultaneously.
Regarding seal verification, quantity confirmation, cargo damage, exception notations on delivery receipts, and the relationship with cargo insurance during devanning operations, these are organized in "What Is Devanning?"
Relation to Drayage Arrangement
Drayage arrangement is necessary for the return of empty containers.
The empty container is transported by trailer from the devanning location to the return point.
Therefore, to meet the return deadline, it is necessary to confirm the devanning completion time, the acceptance hours at the return location, and the availability of drayage vehicles.
Even if devanning finishes in the morning, the container may not be returnable on the same day if a drayage vehicle cannot be arranged. Also, if the return location is congested or has limited acceptance hours, timely return may not be possible.
The overall drayage process, vehicle arrangements, waiting charges, and precautions for heavy or special cargo are organized in a separate article titled “Drayage.”
Container Condition Check at Return
When returning an empty container, the container’s condition may be inspected.
Damage to the floor panels, dents or holes in the walls, door malfunctions, dirt, odors, or traces of liquid leakage could result in cost claims as container damage.
To determine whether damage existed before devanning, occurred during transportation, or happened during the devanning process, photographic records at gate-out, before devanning, after devanning, and at return are important.
If any abnormalities are found with the container, it is advisable to report them to the freight forwarder before returning the container.
Details on how to inspect container damage, its relation to cargo incidents, verification of repair and cleaning costs, and precautions at return are organized in the separate article "Container Damage."
Relationship with EIR
When returning empty containers, an equipment interchange receipt (EIR) may be involved.
The EIR may record details such as the container number, return date, return location, container condition, and presence or absence of damage.
If damage is noted at the time of return, verifying damage costs later may be required.
To confirm what was recorded at the time of return, whether pre-existing damage or newly recognized damage, the EIR and photographic records are important.
The interpretation of EIRs, handling of records at pickup and return, and their relationship to container damage are organized in detail in the separate article "Container Damage."
Common Misunderstandings About Empty Container Returns
| Common Misunderstanding | Actual Consideration | Practical Notes |
|---|---|---|
| Devanning the cargo completes the import FCL process. | Completion requires returning the empty container to the designated location and confirming no delays or damage issues remain. | Manage not only the delivery completion date but also the empty container return date. |
| The empty container can be returned to any nearby depot. | The return location is specified depending on the shipping line, NVOCC, container type, and return date. | Confirm the latest return location and avoid reusing return locations from past cases. |
| The return date is the day devanning is completed. | The return date is usually the date the empty container is accepted at the specified return location. | If the container is returned after the return location’s acceptance hours, it may be recorded as the next business day. |
| Detention no longer applies once the cargo has arrived. | Detention charges may apply if the empty container is returned late, even if the cargo has arrived. | Manage container retention after delivery. |
| Demurrage, Detention, and Storage all mean the same thing. | They refer to different time periods and locations. Costs differ based on whether the container is inside the CY, after gate-out, or in storage. | Check the applicable period and place rather than just the cost name. |
| If the return location refuses the container, there is nothing that can be done. | Pre-check the reception conditions and congestion at the return location. Even if reception is refused, alternative arrangements should be considered. | Confirm return location changes, reception hours, and reservation requirements in advance. |
| Container damage can be checked after returning it. | Without photos before return and records before and after devanning, it is difficult to identify when damage occurred. | Keep records at gate-out, before devanning, after devanning, and upon return. |
| For multiple container shipments, it is sufficient to check return status all at once at the end. | Detention charges and damage checks occur for each container number. | Manage deadlines, return locations, return dates, and conditions individually by container number. |
Checklist for Judgment at Different Confirmation Stages
| Confirmation Stage | Party to Confirm | Items to Confirm | Actions if Issues Are Found |
|---|---|---|---|
| Before CY Gate-Out | Shipping Line, NVOCC, Freight Forwarder, Drayage Company | Scheduled Gate-Out Date, Free Time, Return Deadline, Return Location | If the return deadline is tight, reconfirm the devanning date and vehicle dispatch. |
| When Arranging Devanning | Cargo Owner, Warehouse, Delivery Destination, Freight Forwarder | Work Date, Working Hours, Personnel, Forklift, Devanning Location | If work conditions are not met, share the risk of return delays. |
| When Confirming Return Location | Shipping Line, NVOCC, Return Depot, Drayage Company | Return Location, Reception Hours, Reservation Requirements, Conditions by Container Type | If the return location changes, reconfirm vehicle dispatch and costs. |
| When Dispatching Drayage | Drayage Company, Freight Forwarder, Cargo Owner | Return Vehicle, Pickup Time, Scheduled Return Time, Waiting Conditions | If no vehicle can be secured, consider alternative trips, dates, or contractors. |
| When Cargo Damage Is Found During Devanning | Cargo Owner, Warehouse, Freight Forwarder, Insurance Company | Accident Details, Photos, Inspection Scope, Work Stoppage Time, Return Deadline | Manage accident confirmation and empty container return deadline concurrently. |
| Before Return | Cargo Owner, Warehouse, Drayage Company, Freight Forwarder | Container Interior, Exterior, Cleanliness, Odor, Floorboards, Doors, Photo Records | If abnormalities are found, report and document before return. |
| After Return | Drayage Company, Return Location, Freight Forwarder | Return Date, Return Time, EIR, Damage Records, Reception Completion | If there are unclear records on the EIR, confirm promptly. |
| When Receiving a Detention Claim | Shipping Line, NVOCC, Freight Forwarder, Cargo Owner | Container Number, Relevant Period, Starting Date, Return Date, Basis for Claim, Cause of Delay | Compare the claim period with actual operation records. |
Common Practical Issues
| Case | Potential Issues | Documents to Check | Practical Notes |
|---|---|---|---|
| The delivery destination cannot accept at the scheduled time | Devanning start is delayed, risking missing the return deadline | Delivery reservation, work schedule, acceptable receiving time, return deadline | Check not only the delivery date but also the expected devanning completion time. |
| Devanning operations take longer than expected | Drayage waiting fees, late return, and Detention charges may occur | Work records, cargo details, handling arrangements, return facility acceptance hours | Estimate workload and operational capacity in advance. |
| Cargo damage is found during devanning | Work stops for inspection and photographing, delaying container return | Photos, inspection records, receipt documents, insurance communication records, return deadline | Separate damage confirmation from return deadline management. |
| The return location is changed | Re-dispatch, additional drayage costs, and return delays may occur | Return location notification, drayage arrangement documents, return facility acceptance conditions | Verify the latest return location and share with all stakeholders immediately. |
| The return facility is congested | Waiting for reception, gate closing, risk of next business day handling | Depot reception hours, congestion information, drayage work records, EIR | Plan returns with ample time allowance for reception. |
| Drayage trucks cannot be secured | Empty containers cannot be returned even after devanning is complete | Dispatch records, vehicle arrangement status, return deadline | Secure return transportation early during busy seasons or before holidays. |
| Container damage is pointed out at return | Disputes arise over repair costs, cleaning fees, and timing of damage occurrence | EIR, photos at gate-out, photos before and after devanning, records at return | Record and distinguish between pre-existing and new damage. |
| Only some containers from multiple shipments are returned late | Detention and damage inspections occur on a per-container basis | Container list, gate-out dates, devanning dates, return dates, return locations | Manage each container number individually. |
Items to Manage for Multiple Container Cases
When handling multiple FCL containers simultaneously, it is necessary to manage the return deadlines and return status for each container individually.
Even if containers arrive on the same vessel, the CY gate-out date, devanning date, return date, and return location may differ. If even one container is returned late, there may be Detention charges or damage inspections for that container.
Therefore, for multiple container shipments, it is practically effective to list the process stages by each container number.
| Management Item | Details to Confirm | Parties to Confirm With | Management Notes |
|---|---|---|---|
| Container Number | The unique identifier for each container | Shipping Line, NVOCC, B/L, D/O, EIR | Detention and damage claims are checked by container number. |
| CY Gate-Out Date | Date the loaded container was moved out from the CY | Drayage Company, CY, Freight Forwarder | This may affect the start date for Detention calculations. |
| Scheduled/Actual Devanning Date | Planned and actual completion dates for devanning cargo | Cargo Owner, Warehouse, Delivery Destination | Differences between planned and actual dates can cause return delays. |
| Return Deadline | Deadline by which the container should be returned without extra charges | Shipping Line, NVOCC, Freight Forwarder | Deadlines may differ for each container. |
| Return Location | Designated depot, CY, terminal, or other return point | Shipping Line, NVOCC, Drayage Company | Any changes to the return location should be immediately shared with all parties involved. |
| Return Date and Time | Date and time the returned container was actually accepted | Drayage Company, Return Location, EIR | Returns after cutoff hours may be treated as the next business day. |
| Damage Status | Presence of damage, dirt, odor, need for cleaning or repair | Warehouse, Drayage Company, Return Location, EIR | Photo records should be cross-checked with the EIR. |
| Additional Charges Status | Detention, waiting fees, re-delivery charges, cleaning fees, repair costs | Shipping Line, NVOCC, Drayage Company, Freight Forwarder | Separate the causes of charges and the specific containers involved. |
Comparison Table of Freight Forwarder's Scope of Involvement
| Category | Tasks Easy to Support | Tasks Not to Conclusively Decide | Practical Measures |
|---|---|---|---|
| Return Deadline Confirmation | Organizing the return deadline based on the shipping line or NVOCC's guidance | Concluding the occurrence of charges without verifying contract terms | Cross-check container number, gate-out date, return deadline, and actual return date. |
| Return Location Confirmation | Confirming designated return locations, reception hours, and reservation requirements | Assuming previous return locations are applicable this time without verification | Share the latest return location information with relevant parties. |
| Devanning Schedule Coordination | Confirming the devanning schedule with the delivery destination or warehouse | Assuming that the cargo owner’s operations will always proceed as scheduled | Pre-check manpower, equipment, and receiving hours. |
| Drayage Return Arrangement | Coordinating return trips, estimated return time, and waiting conditions | Assuming that same-day return after devanning completion is always possible | Simultaneously confirm return location reception hours and vehicle availability. |
| Container Condition Confirmation | Encouraging photo records, EIR confirmation, and damage reporting | Determining damage responsibility without physical inspection | Organize records at gate-out, before and after devanning, and upon return. |
| Detention Charge Verification | Organizing charge periods, return dates, delay causes, and contract terms | Concluding claims are correct or unjustified without verifying basis | Cross-check work records, EIR, dispatch logs, and return records. |
Scenario 1: When Devanning Is Delayed and the Return Deadline Approaches
If devanning operations at the delivery destination are delayed and the planned devanning is not completed, the return of empty containers may also be delayed.
In this case, even if cargo receipt has progressed, the container will not be empty and cannot be returned. If the return deadline is missed, additional charges such as detention fees may be incurred.
The freight forwarder should confirm the expected devanning completion, the receiving hours at the return location, and the availability of drayage return trucks, and take necessary actions such as extending working hours, assessing cost impacts of next-day returns, and notifying all parties in advance.
Scenario 2: Return Location Changed at the Last Minute
Due to shipping line or NVOCC operations, the designated return location for empty containers may be changed at the last minute.
A change in the return location may affect the drayage distance, required time, acceptance conditions, and additional charges. In some cases, same-day return might become difficult.
In such cases, it is important to document the notification of the change, the time of change, communication records with the drayage company, and whether additional charges apply, so that the causes for return delays or cost increases can be verified later.
Scenario 3: When Cargo Damage Is Discovered During Devanning
If damage, wetting, or contamination of the cargo is found during devanning, it is necessary to take photographs, inspect the cargo, and notify the insurance company and relevant parties.
If work is halted to confirm the incident, the return of the empty container may be delayed. However, rushing the damage confirmation process could result in insufficient preservation of evidence of the cargo damage.
In such cases, managing the documentation of the cargo damage and the deadline for returning the empty container should be done concurrently. As needed, temporary storage of the damaged cargo, resumption of work, changing the return shipment, and sharing the risk of Detention charges should be arranged.
Scenario 4: When Container Damage Is Noted Upon Return
When returning an empty container, damage such as floorboard damage, dents in the walls, holes, stains, odors, or signs of leaks may be identified.
In such cases, it becomes important to determine whether the damage existed before import, occurred during transportation, or happened during the devanning operation.
Photos taken at gate-out, before devanning, after devanning, as well as the EIR at return should be reviewed to pinpoint when the damage occurred. If records are insufficient, confirming responsibility for subsequent cost claims may become difficult.
Scenario 5: When Return of Only Some Containers Among Multiple Containers Is Delayed
When handling multiple imported FCL shipments, it is not always possible to devan and return all containers on the same day.
Return dates may be staggered due to reasons such as different delivery locations for some containers, a large volume of devanning work, different return destinations, or a shortage of return vehicles.
In such cases, rather than considering the entire shipment as "delivered," it is necessary to manage return deadlines, return dates, return locations, damage status, and additional charges on a container-by-container basis. Even a delay of just one container could incur Detention charges for that specific container.
Points for the Cargo Owner to Note
The cargo owner must prepare not only to receive the cargo but also to return the container in an appropriate condition.
It is necessary to secure devanning workers, forklifts, devanning space, storage space, and work hours, and to empty the container within the scheduled time.
Also, caution is needed if the container will remain at the delivery location for an extended period. If the status is "cargo not yet devanned but will be handled later," there is a risk of exceeding the container return deadline.
In FCL import operations, not only the cargo receipt date but also the empty container return date is an important management item.
Notes for Freight Forwarder Single-Source Arrangement
When a freight forwarder handles import FCL through a single-source arrangement, the empty container return marks the final stage of the import process.
CY gate-out, delivery, devanning, return location confirmation, return deadline, and detention charge conditions are managed as an integrated process.
The cargo owner should be informed not only of the scheduled delivery but also of the expected devanning completion and the empty container return deadline.
Delays in container return can directly lead to additional costs, especially for shipments with short free time, deliveries with limited acceptance dates, or multiple-container shipments.
Practical management of drayage, devanning, and empty container return for import FCL as an integrated process is organized in another article dealing with single-source import FCL arrangements. This article focuses primarily on the meaning and key points of empty container return itself.
Summary
Empty container return refers to the process of returning containers emptied after import FCL devanning to the location designated by the shipping line or NVOCC.
Although this step may not be apparent to the cargo owner after receiving the goods, delays in return could result in additional charges such as Detention fees.
When a freight forwarder arranges through transport, it is necessary to manage CY gate-out, devanning, return location, return deadline, container condition, and EIR as an integrated process.
The designation of return locations reflects operational factors including the shipping line’s or NVOCC’s empty container repositioning management, regional empty container imbalances, and depot receiving capacity.
In import FCL, the practical completion of the operation is not just removing the cargo but also properly returning the empty container and confirming that no Detention fees or container damage issues remain.